Before the floor slabs can be placed it has been necessary to lay the drainage under the slabs. Also some ducts have been placed to allow for future services installation.
Hardcore and a damp proof membrane have been laid so that the floor slab reinforcement can be placed and the floor slabs cast. The floor slabs have been cast.
The concrete blocks and facing bricks have been delivered to site and work has started on the walls.
Steel work for the roof has been measured on site and fabrication is in progress.