From London Rd bridgeDecember 2011


It is now 6 months since the planning conditions were discharged. We have made significant progress over that period and it is time to take stock. 

dumper and minidiggerPreparations for the permanent fence took another step forward this weekend as we removed the section of hedge closest to wharf.

3rd November 2011

gate detailThe materials for the new permanent site fence have been ordered from Betafence today.

October 2011

Mini digger and dumperAfter numerous sessions that have ended with aching backs a few of us have dipped into our wallets for a sure fire cure to back pain - mechanical excavator and dumper. 

October 2011

GrassAfter a period of activity October has been a month to take stock. The wildflower meadow mix sown in September has germinated well and is gradually greening the eastern end of the site: definitely a success.


Wetland meadowAbout one third of the overall plot of land, at the east end of the site, will be cultivated to encourage a wild flower meadow to develop.  As we have started to sow this area opportunities have presented themselves to try to encourage more diversity.